Texas A&M University- West Campus
1 Replace (3) 400hp boilers
This project requires the replacement of 3 existing HW boilers with
3 new Owner furnished boilers HW boilers. The existing boilers were
removed from service and handed over to the Owner. Additional associated
work included: the fabrication and installation of a 14 boiler
mains, and 10and 8 boiler piping, combustion air and
new flue piping for the new boilers, electrical, roofing, concrete
pad provisions/extensions, insulation, industrial grade instrumentation.
University of Texas - Pagenkopf Laboratories
This project involved the renovation of
an existing laboratory facility located on the 5th level at Welch
Hall. MPS was responsible for all the mechanical, plumbing work
specified on the project.
Subcontractor to DPR Construction - $195,000.00
RMMA Airport Underground (Pre-insulated)
Chilled water system. (City of Austin)
This project involved the fit-up and welding
of approximately 6500 feet of 30, 24, 18 and
12 pre-insulated piping. 100% welds on the system were tested
using the Dye Penetrant Testing system, and 30% of
the welds were X-rayed. Std. Wt piping and fittings were utilized
for the systems
Hobby Chiller Activation PH 2 (City
of Austin)
This project involved the modification
of the existing Condenser water system supporting the Central
Plant for the Austin Energy District Cooling for Down Town COA.
MPS installed (2) 60hp condenser water pumps, and the associated
18 piping system.
Freescale Gowning Room
This project involved the provision of
a new mechanical/process system in a new Clean room at Freescale
(Oakhill campus).
Freescale VOC Upgrade
This project involved the replacement of
an existing VOC system. This project was 65% ductwork, 40% rigging,
and 5% plumbing.
Samsung Semiconductor Boiler Feed-water
System Modification
This project involved the modification
of the existing boiler feed-water system. The modified system
is designed to operate at 225psi. The modified system utilizes
an in-line steam heat exchanger for the pre-heating of boiler
feed water.
Stephen F Austin State Office Building
9th Floor Renovation (State of Texas)
This project involved the installation
of a new mechanical system for the 9th floor of this building.
The majority of work in this building involved the installation
of new ductwork.
Texas Department of Health - 7th Floor Laboratory
Renovation (State of Texas)
This project involves the installation
of new mechanical and process plumbing systems to facilitate the
installation and operation of a new Laboratory on the entire 7th
Level of the TDH building.
University of Texas AHU Replacement
@ Jester Dormitory
This project involved the replacement of
(2) Owner furnished air-handling units; one of the units was an
OAU that required the addition of shop fabricated coil casings/framework,
etc. The timeframe to Substantially complete the project was approximately
4 weeks (after the units were delivered to the job site). Liquidated
damages for the project - $11,000/calendar day.
The project was completed on schedule.
University of Texas Hal Weaver Power
Plant Steam By-pass/Quench System
This project involved the installation
of a high-pressure (300psi) PRV steam system. The pressure reducing
valves were furnished by UT. In addition to the 16, 18,
30 and 36 steam piping provided by MPS; 48 carbon
steel pipe was installed up to an MPS manufactured 8 diameter
Quench vessel.
Hobby Chiller Activation PH-III (City
of Austin)
This project involves the provision of
a new chilled water pump and associated piping; the replacement
of 14 check valves with spool pieces, and new control modifications.
.
William P. Clements State Office Building
Cooling Tower Replacement
This project involves the replacement of
a 6-cell cooling tower (4,200 ton capacity) atop a 17 story building.
The replacement will involve street lane closures in Downtown
Austin, temporary cooling tower installation, controls, piping,
extensive rigging, demolition, electrical, and controls.
|